deadline column

2 replies [Last post]
Ahmet Tuter
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

i am able to put in a date value to deadline column but it does not seem to affect any floats or finsih dates. how does this deadline colmun work?

Replies

Ahmet Tuter
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

i did not create it myself. i am using 8.4 version of p6. it was a standard column. can anybody help?

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the forward and backward passes  along with the calendar, logic, durations and constraints determine the dates. There is no such thing as a deadline date column unless you created it yourself. It is not a standard column.