Good day, I use MS project and currently try to move to Primavera. But there are some things that I can't do in Primavera. For example in linked photo (
http://imgh.us/MS_Project.jpg ) you can find screenshot from MS project where I allocated resource to activity and entered planned work load by every day and then entered actual work for every day.So I can see on which date I worked more and what was total plan/actual work. But I can not do the same in Primavera. The only thing I can do is to enter planned work for every day. Or enter number of days and let Primavera distribute work hours based on Curve I select. I can't enter actual work for every day only remaining part. So that means can only see in total what was overwork for example and for daily tracking I have to use excel.
May be I do not know something and you can help me with that? http://imgh.us/MS_Project.jpg