Resource Leveling

3 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

How to make Primavera does not revert the original schedule when re-schedule the program after resource leveling is done.

Best,

Moutaz

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you are correct sorry I mis read your post. I thought that you wanted it to revert back. I think you have the answer now anyway. That is where the setting is either way.

moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks Zoltan, but it is the opposite you check "automatically level resource each time you schedule project" in order not to revert to the original schedule.

Best,

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the leveling option make sure that automatically level resources each time you schedule a project is unchecked

also under the scheduel calculations F9 Options make sure that Level Resources during schedueling in NOT checked

Scheduling the project (without leveling it) will remove any changes to dates that were made by leveling the project.