Applying Hard Constraints to a Schedule in Primavera P6

1 reply [Last post]
Emily Foster
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Here's a guide on how to apply Hard Constraints to a schedule in Primavera P6 http://ow.ly/FxEof

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Emily

Thanks for this guide.

The examples of "External Constraints" - Weather and fish breeding are best set on the calendars.

Asta PowerProject is more realistic as it will not allow negative float - the constraint has to be adjusted/removed before the true completion date is displayed.

My approach is to never use constraints at all.

Best regards

Mike Testro