Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual Finish Date vs Percent Complete

7 replies [Last post]
Tom Tom
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 17 Aug 2014
Posts: 31
Groups: None

Hello All,

    Is there a way to to claim the completion date for an activity without declaring it 100% complete. Everytime I check the finish date box Primavera automatically declare it 100%. 

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can still give the activity 100% complete and have an actual finish date but leave the cost at a vlaue less than the budgeted amount.

Tom Tom
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 17 Aug 2014
Posts: 31
Groups: None

I tired that but it didnt do what I wanted. My EV calculation is based on Physical % complete

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Ah now you have point out the real issue. What you are talking about is unlinking the physical progress from the costs for billing for activities.

Go to the projects directory look at the calculations tab uncheck recalculate actual units when duration % complete changes 

Tom Tom
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 17 Aug 2014
Posts: 31
Groups: None

The contract document allows us to claim actual complete date for certain activites without claiming 100% complete so as not to restrain successor activities. This is for activities completed but we can not bill 100%

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what you are asking to do is not logical look at your wording you want to "CLAIM" a completion date but you do not want to say that it is 100% complete. If it is NOT 100% complete then you cannot CLAIM a completion date. This is illogical. What you can do is say that the activity is 100% complete but NOT CLAIM a completion date.

By definition what you are trying to do is not correct.

Is there some reason why you want to do this ? Maybe you need to use suspend and resume or maybe you need to split the activity into 2 activities.

 

Yanqing Gong
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 20 Mar 2012
Posts: 10

Hello Tom,

        you can use the "Physical % Complete" or "Activity % Complete", when you check the finish date box, the progress of these two columns will keep unchanged.

Paul Harris
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

If a task is finished it is 100% complete, if it is not finished it is not 100% complete and all scheduloing sofwtare works this way.

You could use a User Defined Field or the Physical % Complete may be set at 100% with an Actual Start but no Actual Finish.

 

Regards

Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia

http://www.eh.com.auhttp://www.primavera.com.auand http://eastwoodharris.com.

Project Control Consultants and Planning and scheduling software book and training material publishers

Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/