Scrubbing "Methodology Data" from an old P6 (i.e. Version 3.5) XER File

1 reply [Last post]
Ryan Rowland
User offline. Last seen 4 years 47 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 11
Groups: None

Is there a way to strip "Methodology Data" from an old P6 file (ie Version 3.5) so that it can be imported into Version 7 or Version 8? Already know the Notepad "Cheat" to get an old version into P6, just not sure about the "Methodology Data" part. The file is only to be used as a template, so data integrity is not terribly important.

Thanks,

Replies

Dieter Wambach
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Ryan,

Unfortunately Primavera modifid some names.

XER is a text format which you can open with any editor. The best for you in opinion will be to print out the old and an xer with a current format.

%T is always the start of a new group. So check the headlines and modify them if different. If some groups are missing, this shouldn't matter.

In the first line you must change 3.5 into e.g. 7.0. As far as I remember the format was the same for MM and PM.

Good luck!

Dieter