Remaining cost & Project Cost are after updating

1 reply [Last post]
Rajashekar Reddy
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 10 May 2014
Posts: 4
Groups: None

 

Hi,

I am new to P6, i am finding difficulty cost, in my program if i am updating the % complete of the activity my earned value is getting updated but my total budget cost and remaining cost are same. remaining cost is not getting updated.

Replies

Ravi Katare
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi,

Are you updating the remaining resource units? If not do it

- Ravi