Actual Cost's Are Not Distributing Correctly

1 reply [Last post]
Brook Bolger
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 30 Apr 2009
Posts: 5
Groups: None

I have a project where the actual costs are not distributed in accordance with the actuial dates for that activity. Instead, the costs are placed on the data date and cause a graph spike. this occurs when the "sort costs by financial period" option is turned off. Does anyone know what causes this? 

Replies

Raymund de Laza
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Brook,

I suggest 2 Things:

1. Try to assign a resource curve on the Resource.
2. Remove and Re-assing the same Resource.

 

Regards,