Cost different after import

1 reply [Last post]
Patrick Osakwe
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 19 Sep 2012
Posts: 17
Groups: None

Hi all,

I have just imported a programme onto my P6 and the total cost is lesser than the one in the programme i imported it from.

Can someone please help? I suspect it's a setting issue but couldnt figure it out.

Regards,

Patrick

Replies

Ravi Katare
User offline. Last seen 9 years 40 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi

It could be plenty of reasons, try to check some things like

1. check duration before and after, if it differ means you have same calender names

2. check planned dates

3. check resource IDs

4. check price/unit rates

 

- Ravi