Display Project Codes in Layout

2 replies [Last post]
Nico Groenendijk
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 3 Dec 2007
Posts: 6
Groups: None

Hi,

in P6 I would like to display some project codes in a print layout. The codes I need are not listed in the selection box.

Could anybody tell me how this works?

Thanks in advance!

Best regards,

Nico

Replies

Gary Whitehead
User offline. Last seen 4 years 42 weeks ago. Offline

Nico,

 

I don't believe you can include project codes in the print layout.

Nathaniel Alexander
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 23 Oct 2011
Posts: 3
Groups: None

Hello Nico,

To add project codes you need to do the following.

1) Go to ENTERPRISE

2) Select Project Codes - A pop up box will appear

3) At the top right hand side you need to click on Modify - This will open the Project Definitions Box

4) Add the Project codes that you require- then close the Project Codes Definitions box.

5) On the top left hand side there is a window - Click on the down key, then select the Project Code Definition

6) You can now add any other codes you need. and close box

7) You then go back to ENTERPRISE

8) Select Projects and select the project you want to add the code to

9) In the bottom layout - select codes and asssign

Hope this helps

Nat