Admin Categories

3 replies [Last post]
Godwin Ifeanyi
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 29 Dec 2013
Posts: 5
Groups: None

Good Day Everyone,

I am new here and i can only say this is the best forum i have seen for a while.

Can any one please explain the effects of the : Baseline type and Unit of Measure tabs in the Admin Categories and which one is ideal for Proper planning output?

 

Thanks,will greatly appreciate.

Replies

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762
Labor and non labor will be automatically in hours. Material type resources units shall be assigned accordingly.
Godwin Ifeanyi
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 29 Dec 2013
Posts: 5
Groups: None

@Raymund de Laza

thanks

 

In the unit of Measure,do we have to specifically chose the type of unit for each resource as per the Materials,labor and non labor?

I am a bit confused when it comesto this.

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Godwin,

Baseline Type is just a labelling function when you add baselines. You can add customized label as you wish.

Unit of Measure is used to unitized Material Type resources.

 

Regards,