Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Which projects are being used by which user?

3 replies [Last post]
Kylee Foster
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Morning All,

 

I know there is a way to see this in P6 rel 7 but I've forgotten.  Can someone remind me please?

 

Thanks and Regards, Kylee.

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

These sort of problems underscore our point that there has not been enough work done to support the P6 System Administrator.  That is why we created PROJECT WATCH.  It monitors and displays all P6 or EPPM transactions in real time.  It has dozens of reports and utility functions as well, including forcing someone off of the system.  You can read more at http://scheduleanalyzer.com/pwatch_brochure.htm.

 To answer your question, pre-version 8 P6 systems require a reboot of the server to fix the problem of a ‘lost’ user who is not logged off.  Version 8 introduced an automatic time-out for inactive users.  Good luck!

Kylee Foster
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Thanks Raymund.  When I do this for one users active project I get an application error. CVRJC-0348-8.

This user does not always log off and closing projects is also questionable.

Does anyone have advice about this error?  What can happen if you don't close/ log off?

Thanks and Regards, Kylee.

Raymund de Laza
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

HI,

File.... Open Project ..... Select the Project ..... then click users on the right side.

 

Regards,