P6.1 Reporting - Budgeted Monthly Cost

1 reply [Last post]
Adelfa Sapinoso
User offline. Last seen 11 years 23 weeks ago. Offline
Joined: 6 Aug 2007
Posts: 23
Groups: GPC Qatar

Dear Planet,

 

How to produce a report where the total budgeted cost is distributed monthly in P6.1? I am only able to produce a report where the activity budgeted cost shows on the first month and not distributed for the whole period :( 

 e.g.                           jan2013      feb2013    mar2013            

               activity101    $1,000        $1,000     $1,000

my report shows: 

                                   jan2013     feb2013   mar2013

                activity101     $3,000

 

Thank you ahead!

Replies

Raymund de Laza
User offline. Last seen 33 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Adelfa,

1. Verify the Dates of your resources if it's the same date as your activity.

2. Verify the Calendar used for the Resource, it may be different from the Activity Calendar as well as the Default Calendar.

3. Press F9 to schedule.

 

Regards,