Problem - Resources being phased after activity completion

3 replies [Last post]
stephen hobbs
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 21 Aug 2006
Posts: 8

Hi

This relates to P6 release 6.0

We are noticing a problem where the resource histogram profiles are running well past the activity completion dates.

Does anyone have some idea as to why this is happening?

We think it may be a software error where a previous resource phasing distribution has not been removed/replaced.

Replies

Andrew Podolny
User offline. Last seen 40 weeks 4 days ago. Offline
Joined: 16 Nov 2004
Posts: 130

Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment:

Khaja Sharief
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path.

Raymund de Laza
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Stephen,

I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource.

 

Hope this will help.