Create a No Predecessor filter in Primavera

2 replies [Last post]
Mohamed zaied
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 11 Jun 2013
Posts: 3
Groups: None

Dear Planners,

How to get a list of activities with no predecessors or successors in Primavera P6 R8.2 ?

Regards,

M.Osama

Replies

sneh kumar
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 26 Jun 2012
Posts: 6
Groups: None

Dear,

When you run the schedule, log the file.

In the schedule log you can see all the activities with no predecessor and successor, activity with constraint, critical activities etc.

 

Hope this will help.

Kumar

Feng Benjamin
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 1 Feb 2011
Posts: 12
Groups: None

Dear M.Osama,

The easiest way would be to apply filters. You can filter activities by setting "any of the following rules", predecessor equals to <Blank> or Successor to <Blank>.

Hopefully that helps.

 