Has your question already been answered?

Get a quicker response; before you post, why not search to see if it has already been answered

Microsoft Project Updating - 2 Weeks Only

No replies
Shane Kelly
User offline. Last seen 1 day 20 hours ago. Offline
Joined: 6 Mar 2018
Posts: 2
Groups: None

Hi All, 

My boss has asked me to provide an update of project porgress for a 2 week timeframe only. This would range from the status date + 2 weeks. When using the 'date range' filter it shows activities that start in this timeframe and finish after it. Is it possible to create a filter to show work complete only in this timeframe. An activity that finishes after this could be 100% complete only within this timeframe but not 100% complete in real terms. Any help or advice would be greatly appreciated? 

Kind Regards

S.K