Project Tracking using Microsoft Project 2010

1 reply [Last post]
Mohd Nazrul Azwan...
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 24 Dec 2016
Posts: 3
Groups: None

Dear all,

I am the Junior Planner from Malaysia. I would like to know how many methods of project tracking that can be used in Microsoft Project? I also want to know how can I do the progress tracking by cost and by time based. Please advise me. If you have any notes or handouts, can forward to me at mohdnazrulazwan@gmail.com

Thank you.

Replies

Trevor Rabey
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

There are various methods employed by various people to track progress in MSP, but some of them are just plain wrong.

Suggestion: practice with just one task. start with the tracking table. Input actuals, then adjust the remaining.

Search for "tracking" on google groups microsoft.public.project