Calendars ^ _ ^

1 reply [Last post]
Shishir Dhatwalia
User offline. Last seen 6 years 17 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

Hi !!

I want to make a calendar in MSP 2013 for which I copied the 24 hrs shift.

Now using exceptions I entered the 4 national holidays which went fine.

I marked all the sundays as Off. Now we have a shift change / off day every 15 days or on  the alternate sundays.

Can I do that using some command or I have to select every alternate sunday manually for the project duration ??

 

 

Replies

Shishir Dhatwalia
User offline. Last seen 6 years 17 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

I did it using the exceptions tab

 

made an exception called "Alternate Sunday"

Then click - details; Non-Working radio button is selected &

used the recurrence pattern.

 

If any other method is there plz let me know.