% work Complete field

1 reply [Last post]
Nqabutho Ncube
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 18 Jan 2013
Posts: 3
Groups: None

I am updating a project whos resource type is material, when I an updating the % work complete its not not rolling up to show the overal percentage work complete.

I have tried to change the resource type to work, how ever its giving me an overload on the resource before I can specify the maximun number of units and its pushing the project competion out by a couple of years.

How do I show the overall total number of physical work (hrs)

Replies

Evgeny Z.
User offline. Last seen 38 weeks 6 days ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Ncube,

1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual).

2) MS Project seem to show correctly all work-related values in summary task

See below

 photo Picture_zps894ccbd7.png