How to calculate % work done

A
Ashik GB 👤 Member for 15 years 6 months

Hi Friends,

I have a small querry regarding how to get the information on calculation of Planned % work done for the particular month from Main Schedule.

For Ex: if the project duration is 365 days from Jan1st to dec31 st with 100% Scope, in that how can i know what is the planned % work for the month of any particular month?

 Please can any one help me for this?

Regards,

Ashik

 

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Ashik

display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field

as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself

Alexandre

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts