Where the professionals network; have you Self Assessed? become a Guild Reviewer? or reviewed Guild Phase 2?

MS Project 2007-Percentage of task in overall project.

4 replies [Last post]
Emerson Soriano
User offline. Last seen 1 week 5 days ago. Offline
Joined: 23 Feb 2011
Content Credits: 5

Hi,

I don't know if this has been posted before but I can't see anything about it.

Without any assignments or progress, how do you get MS Project to show what percentage of each task is on overall project?

For example; one task is 10% of the project, next task being 60% & the last task is 30% - not as in completion.

If this makes any sense, can someone please help?

 

Many Thanks

Emerson

Replies

Alexandre Faulx-B...
User offline. Last seen 1 day 9 hours ago. Offline
Joined: 20 Jan 2003
Content Credits: 1032

Emerson,

to display the % complete on the Project Summary Task, open the Bar Format dialog (double clic the empty space of the Gantt Chart for that), select the Project Summary Task, clic the Text tab and add the % complete at one end of the bar

you will get an average value of the different % complete values related to the individual tasks of the project

Alexandre 

Emerson Soriano
User offline. Last seen 1 week 5 days ago. Offline
Joined: 23 Feb 2011
Content Credits: 5

Hi Trevor,

Sorry for my confusion, I've had to use excel in the end.

Thanks for your help.

 

Emerson Soriano
User offline. Last seen 1 week 5 days ago. Offline
Joined: 23 Feb 2011
Content Credits: 5

Hi Trevor,

Sorry for my confusion, I've had to use excel in the end.

Thanks for your help.

 

Trevor Rabey
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 29 Nov 2005
Content Credits: 491

Whoa there. I am afraid your question just does not make sense. What do you mean by a task being some % of the project, and each task being some various different % of the project? A % has to be a % of something. There has to be a fraction with a numerator and a denominator. Something about a task can be some % of something about the project but what might that be? The project might involve 100 m3 of concrete altogether and one task might involve 10 m3 of concrete, so it is 10% of the total concrete. Your software only knows about duration, work and cost, and any task wil have a certain amount of duration, work and cost, which will be a fraction of the total project duration, work or cost. Hope this helps.