Critical Path and Rescheduling

4 replies [Last post]
Bill Joshaf
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 27 Jun 2005
Posts: 33
Groups: None
Can any PP give me the steps to do rescheduling the plan and creating Critical Path in MS project please?

Thanks

Replies

Bill Joshaf
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 27 Jun 2005
Posts: 33
Groups: None
L.E.N thanks for good options
L.E.N. Lewis
User offline. Last seen 2 years 1 week ago. Offline
Joined: 2 Aug 2007
Posts: 47
Groups: None
You have several choices:

1. View | Gantt and set the Filter to "Critical" to see just critical path tasks.

2. View | Tracking Gantt will show all tasks with Critical Path tasks shown in red on the Gantt chart. Again, you can set the filter to "Critical" if you want to see just those tasks.

You might also want to look at Tools | Options | Calculation-tab to adjust the amount of slack from 0 to perhaps 1 or 2 so that tasks with only a day or two of slack will also be shown as critical.
Bill Joshaf
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 27 Jun 2005
Posts: 33
Groups: None
Thanks Briole