Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

manpower not mentioned.

3 replies [Last post]
Arun sangwan
User offline. Last seen 12 years 5 days ago. Offline
Joined: 24 Nov 2009
Posts: 6
dear members,
i have a gone through all the rates but i have query regarding the manpower involved in any of the acitivity is not mentioned.is it standard w.r.t 1+1...


Please clarify

with Regards
Arun sangwan

Replies

Rafael Davila
User offline. Last seen 1 day 5 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Maybe it is useless, production rates without crew definition is meaningless.

1-Production rates are dependent on the crew composition.
2-Crew composition and output is not limited to labor but to tools and equipment.

No wonder so many schedules out there that make no sense, production rates taken from the air without any consideration to the manpower loading, tools and equipment used.

The following production rates include not only placement but also forms, rebar installation, placement and finishing. So you got to start with a clear definition on what is included and what is not, then you need to know your crew composition. What if you use two crews, what if you use an unbalanced crew that provides you with more production per day but with a lower productivity?

production rates

If PP is not to provide the information as to make any sense, better not to provide it. Without crew composition production rates can be anything.

Look at the following PP production rate.
Concrete Placement - 16.0 - m3/day
For placing a 1,000 m3 mat foundation this translates into 62 days of concrete placement !

Just don’t use them.
hand excavation
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
manpower? - you have to assign it
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Arun,

Your question is not very clear. You need to specify following
a.List of activities.
b.Sequence of activities
c.Resources
d.Durations

then you develope the schedule.

With kind regards,

Samer