The Ould Prod-Rates...

2 replies [Last post]
Darrell ODea
User offline. Last seen 18 years 10 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 174
Groups: None
How did the ould production rates caper work out???
Have Planning Planet begun to qualify any data they have?
Or is it all still guess work?????

Must be honest, havn’t look up any rates recently.
Would not use unless they are qualified.

Darrell

Replies

Ernesto Puyana
User offline. Last seen 7 years 35 weeks ago. Offline
Joined: 12 Jan 2001
Posts: 111
Groups: None
This last comment brings out an important issue about prod. rates: Unless you know the crew composition, data is useful only for budgeting purposes, but not for activity duration calculations.
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Agree with tthe previous comments ; also something is lacking number of crew should be included. example laying of cable : prod rate 6 lm / hr . but no. of crew is not included.