Civil Scope of Work (SOW)_Construction Phase_Underground railway project

1 reply [Last post]
Winner YOUSMAN
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 4 Mar 2011
Posts: 3
Groups: None

Dear all,

I need a help to find the scope of of work for civil work in construction phase in underground railway project.

the project is located in a modern and busy city.

Which methodology that I have to use cut and cover method or tunneling?

I wish you are wiling to share your data which inform the civil scope of work systematically.

 

Thank you

Best Regards

W.Yousman.

Replies

safinaz ALI
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 28 Nov 2010
Posts: 6
Groups: TILOS

Dear Mr. W.Yousman,

With reference to your post that you were asking about the better method of civil work construction phase in underground railway project.

Your choice should be follow the next factors.

1-Soil mechanics investigation reports; which method is reliable for land soil specifications.

2-Tunniling method is higher cost than cut and cover method.

(If i have more time i'll provide you with detailed information and referenced data ASAP)

WBR

Safinaz