how to plan and schedule

No replies
rahman A
User offline. Last seen 10 years 18 weeks ago. Offline
Joined: 17 Dec 2013
Posts: 4
Groups: None

Iam Rahman from India. Graduated Mechanical engineer passed out in 2012 currently working as Planning and billing engineer trainee in a small firm for an expansion of Petrochemical plant. I have lot of doubts kindly please help me because am a fresher having only 1 yr in this field.

my duty is only in PIPELINE . We are using MS Excel software only .
Our company is taken to execute this project. The project includes 80000 Inch dia piping fab & erec , structure fab & erec 240 metric ton, Equipment erec 680 Ton.

So please help me me how to plan & schedule this 80000 Inch dia.
Please send me related documents.