Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Concurrent Delay: muti shipment materials, what if the start was delayed and fin. delayed but not in the middle?

No replies
John Reeves
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 10 May 2013
Posts: 246
Groups: None

Concurrent Delay: muti shipment materials, what if the start was delay 30 days in the start, most shipments came in as needed first 50 days AS NEEDED for 100 days of construction, then the last shipments were delayed 20 days (due to failed qa/qc testing) on day 90 - and yes on the critical path. Do you get 240 Days of Concurrent Delay (yes other delays) or do  you only get 40? Can the owner compel the contractor to keep it 1 activity which makes it look worse?   If 1 bar, really is that long.