Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

concurrency example

3 replies [Last post]
Bialla Rafiq
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 19 Oct 2017
Posts: 16
Groups: None

Hi 

i have illustrated one example here, can someone comments and advise the concurrent delays- contractor not asking prolongatin cost , however penalites will be reduced if concurrency in the contract. 

5168
extension_details.png

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Baila

Read Jeremy Fearnsides recent article on LinkedIn regarding concurrency using FIDIC red book in the Middle East jurisdiction.

Best regards

Mike T.

Bialla Rafiq
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 19 Oct 2017
Posts: 16
Groups: None

Dear sir 

Thanks for your response,  i read the contents of this case. 

The parties agree on certain bespoke amendments to JCT Design clause 2.25.13(b) and hence award of extension of time was dealt accordingly. 

But FIDIC conditions of contract does not have such requirements under the contract.  The risk of concurrent delay is not allocated in the contract document , is it fair to consider the dominat cause approach and not to award time to contractor for the delay appear concurrent to employer. 

TThanks 

 

Bilal

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Bialla

If you are in the UK then the current ruling is that the contractor gets EoT for week 24 plus costs.

He pays LAD's for wekk 16 to 23 and no costs.

This is because of the new ruling on North Midland v Cyden which brought us back to the dominant delay principle.

Other more sensible countries will apply an apprtionment of the different delays - more or less as you have shown in your bottom line.

Best regards

Mike Testro