Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Preparation and Evaluation of Acceleration Schedule

2 replies [Last post]
Dimple Dean
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None
Hi All, Contractor agreed to submit acceleration schedule.What I understand about the acceleration is if the project delay is 8 months, and if Contractor agreed to accelerate in 4 months, they need to compress the schedule from 8 months to 4 months.If the Contractor agreed to submit acceleration, would it be from the current updated schedule and compress the schedule?How to evaluate acceleration programme and costs that are associated with it? Many Thanks!

Replies

Dimple Dean
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None

thank you very much Mr. Mike

Mike Testro
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Dimple - Welcome to Planning Planet.

There is no point in putting acceleration measures on completed work so you must concentrate on work in progress.

Take the current schedule that shows work to complete and take a histogram of the planned resources needed to complete the works in the 8 month duration. Set this data into a spreadsheet.

Now you can concentrate on the acceleration methods - DO NOT just shorten each bar to achieve the result but concentrate on:

1. Working Hours inc Overtime and Weekends.

2. Changed work sequences - extra gangs deployment.

3. Changed calendars - weekend working - multi shift working.

All the time make sure that:

4. The gang deployment is NOT overcowding a work zone.

5. The crane and distribution kit can cope

6. You have lighting in place for night work and your elecricity supply can cope

7. Welfare facilities are adequate for the increased work force

When complete run another histogram to set alongside the original to calculate the extra costs involved.

If after all this you cannot see a 4 month result then DO NOT try to fix it.

Best regards

Mike Testro

PS Don't forget that you cannot accelerate curing times unless you change the mix contents