Delay Analysis

Dera all,

I am not an expert in delay analysis .I just have a basic  doubt reagarding my project .it have 4 phases & Critical Phase is phase 4.Now

Phase 4 is delayed from client side & is still delaying from client side .Other 3 phases having float .Now  What my understanding is  the project delay is mainly due to phase 4 delay .EOT  will be equal to phase 4 delay .can we consume all the float available in other 3 phases .Is there any chance that any delay in other phases  from our side will reduce our chances for EOT claim which is equal to phase 4 delay which is critical.

Thanks & Regards

SV

M
Mike Testro 👤 Member for 20 years 5 months

Hi Gary

Glad you picked this one up before me.

Hi Sankar

Whatever the cause of the delay the Contractor has the duty to mitigate the effect on the completion date(s) so squandering available float is not an option.

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 2 months

In response to your question:

1) To some extent, it depends on your contract -If you are applying for EOT in terms of relief from LADs, then it will depend on wether the LADs are applied in part to the completion of each of your phases, or to completion of the project as a whole. If you are applying for additional delay costs, these may have to be a proprotion of your overall prelims associated with phase 4, rather than the entire project.

2) Your say "project delay is mainly due to phase 4 delay." If some of the delay is not client delay, things get a lot more complex, and it will depend on the specifics of the delay -e.g. is it concurrent delay?

3) You need to check your contract, as the float on phases 1 2 & 3 may belong to the contractor, the client, or the project

4) Depending on all of the above, you may be able to use up your float on the other 3 phases without impacting on your EOT claim for phase 4. This is often called "pacing". If you are going to do this, make sure you have informed the client of your intention, and the justification behind what you are doing.

 

I am not an expert in delay analysis either. I am sure others with more experience in these matters will also respond.

G
Gary Whitehead 👤 Member for 17 years 2 months

Sankar,

 

Please only click on the "Save" button ONCE when posting a message. If you click it 13 times, you make 13 posts.

 

I'm now going to delete the other 12 posts.

 

Thanks,

 

Gary.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts