Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

work program revision in accordance with approved E.O.T

4 replies [Last post]
Mai Tawfeq
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 4 Mar 2010
Posts: 96
Hi Dears:

when the project owner approved extension of time and contractor instructed to revised his plan accordingly :

which one of the following path should revised?

1. The target baseline .
2. Or the updated program considering the data date is the first date of claim arising .

Please advise.

Thanks with a best regards.


mai

Replies

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Vand

Welcome to PP

Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used.

The other 3 are applicable to Forensic Analysis.

Best regards

Mike Testro
Vond Kye
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 29 May 2010
Posts: 5
Groups: None
Mai,

It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mike’s reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT.


Regards

Vond Kye
Mai Tawfeq
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 4 Mar 2010
Posts: 96
thanks.
Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Mai

Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date.

Save the file as Baselie EoT 1 and use that file for future contract progress and updates.

Best regards

Mike Testro