Hi All
Im doing the analysis for Employer
I have the foll:
Approved Baseline(BL)
Monthly Updated Programme(MUP)
Several delay events(Employer & Contractor)
Initial issues like site access,design information were used to conduct an interim assessment for time.
I used the impacted planned method (on the BL)because the monthly updates from Contractor have changed durations, resequencing of works etc according to the evolving situation and delayed completion dates. These have not been approved.
The impacted planned analysis gave good results I believe, and I have tried to build in as-built data as much as possible.
However, since the situation is changing, the BL does not reflect the actual so much anymore.
Soon, I may have to do another round of assessment and Id like your inputs, as to what can be done. Continue with impacted planned or use monthly data for TIA or any other method?
What can I do to ensure the Monthly updates are useful for me? Any suggestions?
Sorry to be lengthy, but Id like to get things in place, so that it doesnt get out of hand.
Please reply giving me a way forward
Replies