Dear All,
Say the Minimum Wages of Labour has gone up while the contract is in force (elapsed duration as on date 40% of total duration). Contractor forwards claims as to certain major items executed during the period the Minimum Wages has gone up like reinforcement cutting, bending, tying etc (labour component 60%), shuttering (labour component 30%), concreting (15%). However, a certain Clause in the Contract categorically specifies rates as firm throughout the project duration, irrespective of increase in cost of material, labour, fuel, etc . In such a scenario is the Client morally responsible for reimbursing the extra cost incurred by the Contractor or can he straight away turn it down citing the contract conditions? If turned down is the issue of such magnitude as can snowball into Arbitration etc.? What are your thoughts on the issue?
Replies