Variations Order

3 replies [Last post]
Raphael Adeyemi, ...
User offline. Last seen 9 years 31 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
I want to know if anyone had been in a situation an error in the BOQ rate is too low with substantial quantities and another item with high rate with few quantities.

The main question is a variation to the item that is priced too low with substantia quantities arose. Also there is a variation order of Omission to the item priced tooo high. What is the best approach for the Contractor to go about this.

Waiting to hear from you guys

Replies

Bolisetti Jogiraju
User offline. Last seen 5 years 2 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Raphael !

Nothing more than what Andrew mentioned.

Cheers
Raphael Adeyemi, ...
User offline. Last seen 9 years 31 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
Thanks Andrew

I guess that is the begining
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Raphael,

Starting position is that you’re stuck with them. You win some, you lose some, that’s the nature of business.

Should a variation (rather than omission) come up you would have to try and argue that the conditions / characteristics that you are now performing the work under is sufficiently different from that you priced to justify a re-rate. That may only apply to the varied work though.