Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

acceleration of the works

66 replies [Last post]
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
In one of the running project, the contractor has accelerated the works him self without any instruction nither from the client nor from the engineer.

The contractor was planning to complete some particulare activites ahead of time in order to demobilize the resources allocated for these activities from this contract and mobilized in another new contract.

The weekly up dated progress reports were showing that the contractor actual progress is ahead of program .

Sudenly the employer has issued some additional works which have no impact on the recent status of the project and can be completed within the original contract period but it will prevent the contractor from demobilizing the resources as he was entrnaly planned.

does the contractor has a right to claim for EOT or not and what are the justifibale reasons.

Please advise me.

Replies

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Rajeev,

Although what you say is correct, the usual problem is that the Contractor doesn’t agree with the current completion date - either because EoT claims have been but in and no EoT granted which the contractor believes is incorrect, or there are EoT claims yet to be settled.

The Employer tries to make the contractor stick to the current completion date, the contractor can’t make the current completion date, or only can at considerable expense which he has no guarantee of getting back. Often after the job the Employer wants to charge LD’s from the current completion date and the contractor doesn’t agree with the date

- and before you know it, a dispute has started.

It’s the first sceanrio above that leads to interesting questions about acceleration, constructive or instructed.
Rajeev Nelliyodan
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 21 Feb 2002
Posts: 28
Groups: None
The Contractor is only entitled to an EOT if the extra work will impact the current agreed or approved finished date.

He is compensated for the additional work ie. for all resources and cost including profit & overhead etc.. for performing the extra work.

It is his choice to use the existing resources or mobilize additional resource to perform this work.This may not constitute and EOT if it does not extend the current longest path.

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Anoon,

There is no such thing as a standard contract. A contract is a legally binding promise by parties to do something - in the context of construction:

Contractor - promises to build what the Employer wants
Employer - promises to pay

The starting point is that the price the Contractor and Employer has agreed includes for EVERYTHING. But as we know, construction projects change or unforessen events occur. Therefore the time and cost of these risks are shared between Employer and Contractor - how that is done must be set out in the contract otherwise, (with a few exceptions), the risk is with the Contractor. Eg quantities are the Employers risk in a full re-measurement contract or under FIDIC, the first 15% change is with the contractor and any greater change with the Employer.

As all construction projects are different and Employers priorities are different, so each contract is different - even standard forms of contract are usually amended to reflect the Employers requirements.

How the programme fits into everything will therefore be a matter of the contract wording, as will the significance of changes to the programme.
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
one of the many things I don’t understand is the Contract, is there anything as a Standard Contract? or is there anything as a Standard Wants? (i.e. wants of the Client), is it possible to classify or categorize the Wants, the Needs, and the Allowable and Practicable?

If you consider the Contract as the "Wants", how do you consider the Program or the Schedule of Works?
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
in my humble opinion (though i’m not really humble), it is not reasonable to say that a Program or Schedule is a contract document by itself. I believe that it is an element (or an obligation as Andrew said) forming part of the contract documents.

Why? because basically a Contract is a promise, and Planning and Scheduling are always uncertain! (until it happened). How can you make a promise on Design/Engineering works beforehand?

For me, a Program or Schedule is a Deliverable! a complex one, which defines the whole deliverables!
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
But isn’t an updated programme, if different from the baseline programme, a change of the baseline programme?

If the updated programme if different, you must have departed from the original baseline programme!!!!!!

Not going to get into a great debate on this subject as the arguments really turn on the exact wording of the contract.

Bijaya Bajracharya
User offline. Last seen 8 years 1 day ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
One needs to absolutely certain what is meant by "programme". Many get confused between baseline programme and update. Baseline programme, generally, can only be changed with proper approval process. But current programme or update is just the current status of the project. It may show late or early completion depending on status of the project. And it should. It is the crystal ball of the project.

Changing the baseline programme would be change in contract terms.

Change in current programme has nothing to do with contract terms. It is part of project management.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
If the programme is part of the contract, and it can be, then for better or worse, it comes under excatly the same rules concerning a change to the terms of the contract, just like any change to any other term in that contract.

Which leads to some very interesting arguments!!!!!!!!!!!

Note - we are talking about a change to the contract terms here, not a change to the scope of works within the contract.
Gary Whitehead
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
absolutely. I’m working on a project at the moment where the client has insisted the programme is a contract document, and any changes made to the logic / durations / etc have to be approved by them.
What happens instead is that the contractor just runs 2 versions of the programme -one representing the actual plan, and another to show to the client once a month. thus the client loses any ability to understand the real progress of his project. I’ve actually sat in meetings where the client berates the cotnractor for the 5 month forecast delay to the project, and the contractor tells them they’re actually planning to come in 2 weeks ahead of plan. totally nuts.
Trevor Rabey
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Andrew, I am definitely with you on this one.

Even if it is a "contract document", what does that mean?

If "contract document" means that each and every detail of it is some sort of a contract promise, and that any departure in any detail is some sort of technical contract breach, then it is ridiculous. A contractor will continuously be in this technical breach right from day 1, because things, hopefully only small things, change.

If not every detail, then saying "contract document" must be accompanied by a very strict specification of which details are the promises.

The idea that the contractor requires the permission of the client to change the program, in any respect at all, could only have been thought up by lawyers. Of course it’s in contracts, but it is ridiculous. The contractor has already assumed the risk of meeting a small number of specific promises, eg the handover date. If the client deprives the contractor of just about the only tool available to manage that risk, ie the program and the ability to plan and then revise the plan as frequently as necessary, the client is the main problem and is acting against his own interests. There may be some things that the contractor cannot change because they are not within his control, such as the dates that the client will supply equipment, and the contractor cannot oblige/force the client to change his dates to match some revision, but that’s all.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
All,

I remember discussing this a while back - most standard forms of contract make the provision of a programme by the contractor a contractual obligation - this does not automatically make the programme a contract document.

In many standard forms the programme is NOT a contract document.
Sherif Fam
User offline. Last seen 12 years 47 weeks ago. Offline
Joined: 18 Apr 2005
Posts: 28
Groups: None
Donald,

I absolutly agree with you.

The Contractor needs Client/Consultant approval, in order to revise the time schedule (even in the form of acceleration). The hidden intentions can be shortening Provisional Sum Items, or earlier appointement of nominated subcontractors; in order to plan a Claim.

Moreover, as you said; CONTRACTUALLY, the Master Baseline is considered part of the Contract Documents; hence, alterations require approval of all parties.


Donald Graham Cowley
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 20 Jan 2008
Posts: 5
Groups: None
ACTUALLY ASHRAF THERE IS ... THE OBLIGATION.

MOST FORMS OF CONTRACT PLACE THE PROGRAMME AS A CONTRACT DOCUMENT WHICH MEANS IT HAS TO BE COMPLIED WITH BY THE CONTRACTOR AS PART OF HIS PERFORMANCE ...

WHILST IT MAY BE TRUE THAT THERE PERHAPS MIGHT BE NO OBJECTION TO GOING FASTER THIS HAS A LOT OF RAMIFICATIONS...NSC’S FOR ONE ...WHOSE TIMING IS FIXED BY THE ENGINEER.

THUS, ANY CHANGE TO THE TIMING (I.E. ACCELERATION) IS CLASSIFIED (MAYBE) AS A CHANGE AND ONE PARTY CANNOT CHANGE A CONTRACT WITHOUT THE OTHERS CONSENT.

ACCELERATION IS THE SAME AS ANY OTHER CHANGE OR VARIATION, EXCEPT BY THE CONTRACTOR NOT THE EMPLOYER / ENGINEER
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear all

we can conclude that the following are the driven activities
in this case:_
the condition of contract.
the approved construction program.
the time of issuing the instruction.
the up dated progress report at the time of given the instruction.
the contractor acceptance /rejection to this instruction.
the contractor;s notification regarding this instruction.
the contractor justification for his case.
the availability of supporting documents and conteporary records.
the client and engineer understanding to the contractor claims
Waleed Mahfouz
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 8 Sep 2007
Posts: 28
Groups: None
As I said before, there is no body hate to finish his project earlier. But, if there are some dependant activities based upon the main contractors activities, so increasing progress won’t help the onwer.
on the other hand, the finacial issues related to the progress will not enforce the owner to pay more than what is planned earlier.
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
i do not think that there is any contractual clauses in the condition of contract can prevent the contractor from accelerating the works by his own wish and no body can object if the weekly up dated progress report is showing that the contractor progress is ahead of program.
Waleed Mahfouz
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 8 Sep 2007
Posts: 28
Groups: None
ANY AGREEMENT SHOULD BE WRITTEN AND AGREED BY ALL PARTIES FIRST. SO THE CONTRACTOR CAN’T CHANGE THE BASELING PROGRAM HIMSELF. HE HAS TO PLAY WITHEN THE TEAM GOAL, NOT HIS OWN GOAL.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
In most contracts the contractor would recover prolongation costs but it’s not a given right too so all I’m saying is, don’t automatically expect that you can.
Joe Hellenbrand
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 13 Sep 2007
Posts: 19
maybe it’s just an american thing (we’re always causing trouble)

but I’ve seen at least two owners but language in their scheduling specs barring the contractor from showing an early completion on the baseline schedule for just this reason. and recently saw an owner lose big on a case similar to the example I used.
Thanks!
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Probably! But not automatically.

A good case to read on this is Glenlion Construction v The Guiness Trust [1988] BLR 39 which deals in some detail the obligation of each party when the contractor shows an early completion date. Summarised below on that point:

Question:
(3) Whether there was an implied term of the contract between the applicant and the respondent that, if and in so far as the programme showed a completion date before the date for completion the employer by himself, his servants or agents should so perform the said agreement as to enable the contractor to carry out the works in accordance with the programme and to complete the works on the said completion date.

HELD:
As to question (3):

No: since it was not suggested by the contractor that he was both entitled and obliged to finish by the earlier completion date and if there was such an implied term it would impose an obligation on the Trust but not on Glenlion.

Per curiam: The unilateral imposition of a different completion would result in the whole balance of the contract being lost. The position would be no different if the obligation imposed on the employer was instead of being absolute, a requirement that meant that the employer should act reasonably.
Joe Hellenbrand
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 13 Sep 2007
Posts: 19
ok play along with me. a contractor says we have developed a reasonable baseline schedule that shows us finishing 18 months early. the contractor anticipates finishing early and saving a lot of money on the reduced field overhead,ect. the baseline is accepted but the owner notes that it does not agree w/ the early completion date that it is too optimistic. the project has problems with the design and these problems delay the critical path of the project. the project does meet the contract completion date but finishes 18 months late in the contractors mind. is the contractor due any damages for the owner causing him to miss the early completion date?
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
The contractor does not have the "right" to finish early. A party must not hinder the other and must co-operate so as to allow the other party to comply with his contracrual obligations. If the contractual completion date is later than the contractors early date, the only obligation on the employer is not to hinder the contractor from finishing by the contract date.

The contractor may, subject to the wording of the contract, be able to claim prolongation costs if he can prove he has been kept on site longer by the employer, eg extra works, but the employer is under no obligation whatsoever, to ensure the contractor finishes by his early date. Unless of course, the employer has agreed to the early completion date.
Joe Hellenbrand
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 13 Sep 2007
Posts: 19
a contractor has the right to finish early unless it is stated otherwise in the contract. If the contractor can show they can finish early then the owner should be careful not to delay that early completion date.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
All comes down to what’s been actually agreed between contractor and client - not what the contractor would like to think has been agreed by by simply showing an early date on a programme.
Joe Hellenbrand
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 13 Sep 2007
Posts: 19
in the US I worked a couple cases where if the contractor indicates in their baseline schedule that they plan on finishing early then that is the date they are shooting for. If the owner delays the contractor delays the contractor from achieving that date the owner can expect a claim for extended overhead and can expect to pay for it.

I’ve seen some owners put in their scheduling specs that no early completion is allowed in the baseline schedule to counter this early completion arguement
Waleed Mahfouz
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 8 Sep 2007
Posts: 28
Groups: None
IMO, The construction is an interactive business, but it belongs to the owner at the end. So all contracts were regulating the works for the sake of the owner. Also the construction is not a matter of time only, but it is financial matter first degree. Therefore, the owner always prepare his payments according to the cash flow curve which is based upon the baseline program. So, the modified cash flow which is based on the accelerated works, wouldn’t be obligatory to the owner.
One can say that the final benefit will end to the owner, but it is unsatisfactory, as the works may depend upon another subcontractor, or supplier. consequently, the early completion date won’t help the owner.

On the other hand, the part of additional works, as we all know that the additional work don’t mean additional time. The only measure is the impact of time schedule, which mean that the float is owned to the project itself and doesn’t belong to any party.
To be continued.
Armando Moriles
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 9 Dec 2005
Posts: 104
Groups: None
Guys,

I would like to add up the ff that might help for a better understanding of my views and hoping not to confuse anybody further:

A contractor’s proposed early project completion milestone is unconstrained date to represent its early completion date. But this unconstrained date is not a release from contracturally required finish date,but is left unconstrained to allow the schedule logic to calculate without hindrance.

Andrew, it really sounds new to me to hear a programme being normally not a contract document. It’s really quiet interesting.

Regards,

Arman
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
James,

As always the parties want all the advantages of a contract, but non of the disadvantages, unfortunately it doesn’t work that way.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf,

Just being lazy, rather than reading all the previous posts, what conditions of contract are they. The provision of a programme is probably a contract condition, that doesn’t make the program a contractual document though.
James Barnes
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
What an intriguing problem. I’m going to opinionate here....

imo Andrew makes a good point;

the contractor may have issued an accellerated programme but my guess is that neither he, nor the client, have formally comitted to it.

Ask the contractor if he would accept LDs in the event that he breaches his own accellerated programme (assuming the extras were not issued) but still achieved the baseline. In fact, I wouldn’t be surprised if the contractor hadn’t included such a caveat in his progress submissions to the effect that he’s not bound by the accellerated dates. On the other hand, assuming that the client were to get some benefit from an early completion (early rent etc), would he proactively share this with the contractor?

*chuckles*

In these circumstances, much as I sympathise with the contractor, I would suggest that the baseline schedule be used.

That said, the contractor has probably made an investment in the accelleration in order to free up his team and, if the client has no choice of other contractors, he should tread a little carefully. Afterall, the aim is a finished project not a courtcase! The contractor most likely wants to free up certain key personell and would accept a scheme that got the extra work done while allowing his PM or whoever to move off to the new job.

It’s more often about politics than contracts, really.
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Andrew,
The program is part of the condition of contract(Clause 14).
Without submitting the program the contractor can not get the advance payment in the begining of the project.
any claims for EOT to be analised and assessed based on the approved program.
Monitoring of the progress during the construction stage is depending on the approved program and the actual % completed of the activites at cetain date.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf:

The first thing is to make sure that the programme is actually part of the contract, not just referred to in the contract documents.

Normally the programme isn’t a contract document. Eg, if it was produced after the contract is made - therefore it didn’t exist when the contract came into being so can’t be part of it! If it is, ie was a document in existence when the contract was executed and incorporated into it, then a whole new set of fun and games emerges.
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Hi,Andrew

As understood,the progam of work is part of the most important contractual documents.

in the light of the above , there is a dispute about your statement that:-
1-showing an early completion on a programme, whethter accepted or not does not automatiaclly entitle the contractor to finish early.
2-because the employer accepts a program showing an early finish date does mean anything on it’s own.

can you varify your opinion contractually assuming that that the contractor for any reasons has submitted his program showing an early finish date .
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Armando’s along the right lines but two important points:

1. Just showing an early completion on a programme, whethter accepted or not does not automatiaclly entitle the contractor to finish early.

2. It comes down to what was agreed when the contract was made. If it was agreed that the contractor was going to try and finish early, it was a realistic possibility and the employer knew this, then the contractor would be entitled to use the early finish date to argue his case. The emphasis being on it something that was agreed. If it was not agreed, just something the contractor showed on his program and was hoping to do, then tough.

3. Just because the employer accepts a program showing an early finish date does mean anything on it’s own. He’s hardly likely not to accept the program on the basis that the project might finish early is he? And it works both ways - the employer can’t complain and charge LD’s if the the project merely goes beyond the early finish date and not the contractual date, the contractor can’t complain that he’s signed a contract allowing variations, which in the normal course of events he’d probably welcome, and the employer, quite correctly under the contract, orders variations, even if that keeps him on site longer.
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Hi,Armando

That is reasonable opinion.

REGARDS
Armando Moriles
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 9 Dec 2005
Posts: 104
Groups: None
Guys,

I seemed to agree with Garry, being the case as an issue of float ownership. In my opinion the float generated during the course of contract execution is not for the sole use of the party generating the float; but as a shared commodity to be reasonably used by either party.

Should the contractor specified in his baseline programme his intention of completing the contract earlier by indicating an early completion milestone dates and accepted by the client, then the contractor may demobilize his resources relative to the accepted early completion dates. In the absence of such, then early demobilization might not be given favorable acceptance by the client and may use his rightful share of the float generated by holding up contractual resources for his intended purpose.


Just an opinion guys!

Regards,

Arman
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Samy,

The principles for working out the EoT entitlement would be generally exactly the same, just applied to the different circumstances. The contract determines these but unless there’s something out of the ordinary then the overriding principle to have in mind is:

"what is a fair and reasonable aggregate period of time from the commencment of the works, for the contractor to complete all of the works"
ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
1-Before issuing the addetional works ,get the up date program to specify the contractor’s own delays.

2-see the impact of the addetional works on the approved base line program.

by compairing the results of 1 &2 you can evaluate the contracor’s entitlments.
Samy Lateef
User offline. Last seen 16 years 28 weeks ago. Offline
Joined: 7 Oct 2007
Posts: 3
Groups: None
Hi Everyone,

I just wanted to ask , what if the scenario went the other way whereby the client issued some additional works but the contractor was behind the schedule???

Please expand on that one.

Thanks in advance.

ashraf alawady
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
Dear All,
Still the case under study and the resoution of minor commtee for disputs still not issued yet.
the contractor refused the engineer judgement to analise the impact of the additional works on the updated programme and the contractor has submitted the impact on the base line programme which has shown an impact of 3o days and now the contractor is asking for EOT 30 days with assiocated cost in addition to that the cotractor is asking for new rates for the additional works based on the average market prices for each item separetly .
The additional works as well as the orginal scope of works have to be copleted on the original contract duration due to the high imporancy and urgency of the said project.
I have sujested to make an amikable settelement with the contractor and we are studing all the possible alternatives in order to avoid raising this case to the court.
Shahzad Munawar
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Rodel and Andrew

You both are correct. It is always advised here that better to seek whatever your contract provisions stipulate and then you proceed accordingly rather than based on assumptions. We cannot implement the same judgment because it varies from contract to contract.
Rodel Marasigan
User offline. Last seen 2 hours 48 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Correct Andrew, we are all just assuming, giving the general views and we cannot judge to say that the other posts are not valid.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Rodel,

There’s a infinite number of provisions that a contract could contain or combinations thereof. A single word in what would otherwise be two identical clauses can have a significiant effect on the meaning of it.

Always the problem on this site, never get to see what’s actually written or the other parties side of the story.
Rodel Marasigan
User offline. Last seen 2 hours 48 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Absolutely agreed if the variation falls within their scope of work and within the capabilities of the contractors as I have mention earlier then the contractor deemed to comply when necessary but negotiation are still within the favour of contractor specially if the client will benefit on it. Please note that “some” condition of contract also states the max limit for variation not more than 10% of the contract scope otherwise will be treated as new contract
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
It’s never simple is it!!!!

Depends what the variation is as to whether it can be "deemed necessary".

It would have to have been "deemed necessary" at the time the contract was entered into, not with hindsight now.

And if it is something so different as not to fall within the scope of the original contract, he needs a new contract anyway.
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
oh by the way, the Client has found a clause in his contract, it states that: "All other items not included or not mentioned in the scope of works but are deemed necessary to complete the intent of the job, shall be borne by the Contractor". so he doesn’t have to pay for the additional works as requested...
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Rodel,

Certainly not a breach of contract for finishing early and the coments are on the assumption that the variation is within the scope of the original contract.

If it isn’t (it is something that is so different from the original contract as not to be considered part of it) then a new contract would be needed - at which point both parties need to agree terms on price, time, etc, etc like any other new contract.

Most contracts have something along the line of "the contractor SHALL forthwith comply with instructions, variations issued...." along with another clause saying "no instruction, variation shall vitiate the contract....." or similar words to the same effect.

Put together they make a variation compulsory - assuming it’s within the scope of the contract in the first place.

I’d be surprised if the contract hasn’t got something like this as one of the fundamental aims of most contracts is to get the work completed or give the Employer a way of finishing if the contractor fails to complete.
Rodel Marasigan
User offline. Last seen 2 hours 48 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Andrew,

There is certain limitation on the condition of contract. It is not always in favour of the client. It is also up to the contractor to accept the risk before signing their contract. I know there some condition that make it compulsory to accept variation but up to bearable boundaries and contractor’s capabilities. If the variation is outside that boundary it is contractors decision whether to accept or not the variation.

On the original post “contractor done the acceleration to the intent of relocating their resources on the other project and demobilized earlier than required”. There is no bridge of contract if they finished earlier than required and as a matter a fact it is the client who will benefit on contractor action and more often the contractor received bonuses by doing this.

On this scenario the client issued a variation to take advantage the opportunities. I often engaged on this kind of event and normally negotiated fairly to cover up the intention or the risk of losing another client. It is always contractor’s decision whether to accept the variation which normally ends up to signing another contract with new rates. For manageable changes it is normal to accept the variation for a reason that it is required and related to their scope of work. In this case EOT is not the issue but the value and risk or if they can deliver it on time.

Rodel
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Gary,

IMHO, it’s not a question of who owns the float? but who prepared the program that calculates the float? Float is simply a product of logics and relationships of activities which is speculative. And most of the time, the Contractor is the one who’s preparing the program / schedule based on his methodologies, strategies and resources which makes the float his reserve.

If I am working with the contractor side (luckilly i’m not), I’ll see to it that my program / schedule has no float at all. If ever there is, I would hide it so that the Customer wouldn’t know about it.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Gary,

The acceleration doesn’ have anything to do with the EoT. If the variation caused the contractor to go past the contract completion date, the contractor gets an EoT. If not he maybe entitled to prolongation costs but no EoT.

And the answer to the second point is no th Employer wouldn’t be entitled to LD’s unless the contract unusually allowed him to set another completion date prior to the original completion date.

The only contract that I know of that expressly gusrda the Contractors terminal float is the NEC. But then that would depend on what was shown on the Accepted Programme.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Rodel,

It is normal that the conditions of contract make it compulsory to accept the variation, there isn’t an option unless the Contractor wants to pay the Employer damages.
Rodel Marasigan
User offline. Last seen 2 hours 48 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
I believed that all views and explanations posted are all valid reasons. The only thing that have been missed is the contractors right to refuse or not accepting the variation if he wanted to. Usually because of good and long relationship between the client and the contractor that needs to maintain that is why variations are normally accepted without hesitation but it also processed on fair negotiations. As stated by Clive, time and cost are being looked at so it will be enough to contractor to cover the losses or his intensions. At the end it is still contractor’s decision to accept the variations. On my point of view, contractors will not live to lost another contract from different clients or suffer more if he will accept variation knowing that he will gained losses more money at the end.
Gary Whitehead
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
No, but nor am I in the habit of expecting to get something for free.
Whether the acceleration happened before or after the variations were issued, has no bearing as far as I can see to the value of those variations.

To my mind, the acceleration by the contractor, being not instructed by the client or really having anything to do with the contract, should bear no impact on any EOT claim. If the client wants 6 weeks more work to be done, he should pay for 6 weeks more work to be done.

On the flip side, if the contractor was failing to meet the completion date, and the client removed some of the scope from the project, enabling contractor to complete on time, would LDs come into play?

I suppose at the end of the day, it all comes down to ‘who owns the float?’
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Gary,

Are you in the habit of paying for something you haven’t asked for.

The Contractor made a decision, totaly for his own commercial benefit.

He was doing a contract, in that contract variations were allowed - there was always the risk that extra work might be ordered keeping his plant etc on site longer. It isn’t a rare thing for extra work to happen on a construction contract, if fact it’s almost an inherent certainty.

He had to weigh up the risks and make a decision - he did. This time it hasn’t worked in his favour but that’s the nature of being in business. Construction is all about risk management - you win some, you lose some.

The contractor will have to go and hire some more plant, source some labour from somewhere to start the other contract (or finish this one). Not the end of the world and a situation every contractor faces from time to time.
Gary Whitehead
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
I don’t have much experience in claims, so apologies if I’m missing something here. But to my mind, if the employer is going to benefit from the acceleration, then he should pay for it.
Appreciate that they did not instruct the acceleration, but with the additional works, the acceleration that was originally to benefit the contractor, would now benefit the client instead. Don’t see why they should get it for free.
Similarly, if the client removed some work from the scope, then he might reasonably request a saving if the completion date wasn’t brought forward accordingly.
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Andrew,

I think Khawaja is working for the commercial side of the Contractor. If he finish early and makes the Customer happy then he can negotiate for a bonus, but this is the Customer’s kindness (if not considered in the contract).

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Khawaja,

If the extra works affected the completion date then yes the Contractor would be due an EoT, but in the information given, we’re assuming it doesn’t.

Why should the Employer be obliged to pay for the acceleration - it’s something he hasn’t instructed or asked for?

If the Contractor had not accelerated but finished on the proper date could the Employer ask for a saving because the Contractor didn’t finish early!!!!!!!!!!!!! I think not.
khawaja uddin
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 59
Groups: None
hi,
why can’t the contractor show this event on the base line program to show its impact on over all completion date.
If it does effect the project completion date ,contractor ,in my opinion has all the right to claim EOT.Though seeing actual staus of the project if however client feels that impact of the event in as built program does not effect the project completion date than eventually contractor has all the right to claim for the acceleration of work ......why ..bcoz the work which was accelerate dby the contractor for his own benifit will go to the owner.
This is a simple case ....but matters how it is presented.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
And generally, the Client is under no obligation to help the Contractor finish early - only to ensure the Contractor can comply with his contractual obligations to finish on he contract completion date.
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
If the Contractor has set his baseline program and have it approved by the Client in the first place, then it is his option to accelerate the works by adding his resources or improve his methodologies to increase his profits and finish the project ahead of schedule.

IMO, additional works requested by the Client that was not considered in the approved baseline schedule, is another story, whether or not it affects the time schedule.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Clive,

And there in lies the difference:

"the contractor clearly identified both at the time of tender... that he had commitments for the dredger"

If the contract was clearly agreed on that basis then that was the agreement, but it doesn’t appear to be the case below.

Clive Randall
User offline. Last seen 16 years 18 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
I had an interesting problem like this some years ago
It was a reclamation project that relied heavily on dredgers.
The tender and contract programme clearly identified that the dredger was to carry out the works over a defined period and at the end of the works the dredger was to be demobilised to another project.
The dredger arrived as programmed completed its works as programmed and was demobilised to another location. The employer then issued an instruction for additional dredging works.
After considerable discussion it was agreed that the dredger would be remobilised when it became available and that the costs for remobilisation were to be included in the valuation of the variation. Equally it was agreed that the works could not commence until the dredger could be remobilised and that prolongation costs were required to be paid.
As I said in my previous post, the contractor clearly identified both at the time of tender and at the presentation of the works programme that he had commitments for the dredger
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf,

Interesting one, as Clive said, not really enough information but the starting point is the Contractor has taken on the contract, which presumably allowed for variations, and therefore tough.

His decision to accelerate and finish early to start another job is his own, a commercial decision which he bears the responsibility for, not the Employer.

As long as the variation properly falls within the contract it is to be valued under the terms of the contract with no regard to anything else. If the contract hasn’t been varied, ie the Employer hasn’t agreed to the early completion then the Contractors taken a risk and this time it hasn’t paid off.

If no express consent from the Employer has been given then the only circumstance in which it might be different is if the Contractor can somehow imply the Employers consent to an earlier completion date, ie that the contract has been varied. Given the Employers desire to instruct the extra work then I think this probably would be difficult.

If the Contractor refuses to carry out the work, validly instructed under the contract, then he is in breach of contract and the Employer can claim damages against him. Oh, and if the Contractor can still complete on time then he is not entitled to an EoT.

What the Contractor is entitled to however, is a fair valuation of the additional works in accordance with the contract and possibly (probably) prolongation costs for the Employer keeping him on site for longer than he would have been. For the details of this, you’ll have to digest the contract and see what it says. I’m sure there are a variety of arguments the Contractor can put forward to enhance the price if he puts his mind to it.

In any case, it is up to the Contractor how he sorts out his other work commitments, it is of no interest to the Employer of this contract.

Might seem abit tough, but at the end of the day the Employer is paying and his interest is in seeing that his contract gets completed, not that Joe Bloggs contract down the road gets started.

Contracts are generally written to ensure performance or that the Employer has sufficient recourse (LD’s, termination rights, bonds, set off provisions, company guarantees, retention, indemnites, condition precedents, insurance) to pay for the work to be completed should the Contractor fail in his performance.

You could end up in a big mess by trying to be accomodating on this one, however tempting and reasonable it would appear. Following the contract might also end up in a different mess but the Employer should at least CLEARLY know where he stands and what remedies are available, should the Contractor dissappear
Clive Randall
User offline. Last seen 16 years 18 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Ashraf
I have added my comment into your mail trust this helps

"In one of the running project, the contractor has accelerated the works him self without any instruction nither from the client nor from the engineer."

I believe the contractor can finish ahead of programme if he so desires without an instruction from the employer representative, NB the client should not be instructing the Contractor
I feel.

"The contractor was planning to complete some particulare activites ahead of time in order to demobilize the resources allocated for these activities from this contract and mobilized in another new contract."

Again the contractor is entitled to do this and hopefully he has made it clear in communications and programmes that this is his intention.

"The weekly up dated progress reports were showing that the contractor actual progress is ahead of program ."

From what you are saying this is a fair and reasonable position to be advising the Client.

"Sudenly the employer has issued some additional works which have no impact on the recent status of the project and can be completed within the original contract period but it will prevent the contractor from demobilizing the resources as he was entrnaly planned.

does the contractor has a right to claim for EOT or not and what are the justifibale reasons."


Please advise me.

This is where it gets interesting,
Firstly can the contractor claim an extension is probably not as important here as whether the contractor is entitled to additional expense and in what quantum for the additional works. My initial take on what you have said is as long as the contractor can complete these additional works within the contract period he may not be able to claim for an extension. However this very much depends on who and how the float is owned. A seperate link deals with this subject very well and I believe a visit to the society of construction law may well be worthwhile to download their excellent document on construction delay protocol.
Notwithstanding this the knub here is the valuation of the additional works, if the contractor could have finished his works early and has showed this in his progress reports and he intended to demobilise early and move to another committed project he would have in my opinion a good chance of placing a premium on these additional works. If I were the contractor and these additional works were likely to cost him a considerable loss I would refuse to accept the instruction unless the valuation terms were explicit ie possibly not using the rates in the bill but new negoitiated rates at this point the client can a)get somebody else to do the work but from what you are saying this may not be possible or b) negotiate a new rate.
However you have provided very limited info on a complex problem, more info will enable more answers to be provided.
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Ashraf,

The right to claim by the Contractor is inherint in the contract. We have to accept this whenever in the opinion of the contractor has the right to claim.

However, whether the claim is valid or not, that should be in the opinion of the client’s representative or by the client itself.

The contractor may not be happy by the opinion of the client’s representative or by the client itself, still the contractor has a lot of options in the contract.

So now, i have no opinion to give further since i do not know the details.

Cheers,

Charlie



Bijaya Bajracharya
User offline. Last seen 8 years 1 day ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
Additional works but no impact on current status of proeject - this can happen only in client’s perspective because in theory extra work means extra effort, extra resource and extra time.

Just like Contractor’s hidden agenda, the Client has hidden agenda as well - in this case - he gets aware of the situation when the Contractor is getting ahead of schedule and then thinks he can use this time to get some additional work done.

If the Client has paid the Contractor to accelerate, then he could ask the additional works to be done in that "saved time". Otherwise, extra works mean extra time.