Power Project Versions

4 replies [Last post]
Fergus Carey
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 27 Feb 2006
Posts: 5
Groups: None
I have received a Power Project programme which I can’t open because I have version 5 and the programme I received is in version 3 or earlier. Any suggestions on how I can remedy this problem? Thanks

Replies

Fergus Carey
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 27 Feb 2006
Posts: 5
Groups: None
Have given up on it. I don’t have maintenance for PowerProject as I don’t use it and I was talking to Asta about the problem. If I had maintenance it is a job for them and would take a few days. PDF will have to do.
Andrew Pearce
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 11 Jun 2001
Posts: 174
If you still have maintenance contact ASTA directly
Fergus Carey
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 27 Feb 2006
Posts: 5
Groups: None
I checked again. I have PowerProject 5 and when I try to open the mail a text box comes up in PowerProject saying "The project is in a version that is too old to be converted. (Before version 3.0)". Any thoughts?
Bijaya Bajracharya
User offline. Last seen 3 years 4 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
If you have version 5 and the programme you want to open is from version 3, there should not be any problem.

But as the latest version is 9, it is not likely that you would receive a programme in version 3. (Or was it 8 instead?).

Anyway ASTA helpdesk is very good in answering the customer problems. So I suggest you contact them.