What is Actuals in Schedule options

3 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi,

I have dealt in P3.1; two options in Scheduling i.e. retained logic and progress override. But P6 have one more options i.e. Actual Dates………What is the logic behind using actuals…..I have read from help menu that Actual Dates will schedule my backward and forward passes using actual dates.
I think Progress override is also of the same use. It will override my logic and use the actual progress to determine the progress of work……..Can anybody explain what is the exact use of “actual dates”

Replies

quartz
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 13 Sep 2010
Posts: 4
Groups: None

Hi,

I am currently migrating from P3 to P6.  In one of our reports - Variance Analyis in P3 filter I can define the filter the following:

if Actual dates Is WR DD-30D DD+0D

where Low Value = DD-30D

          High Value = DD+0D

In P6 the Actual dates is not there...  it was changed to something. I tried to use the Planned  Start or the Actual Start but the result was different than I expect. Can you help with this? Thanks.

 

Regards,

quartz

quartz
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 13 Sep 2010
Posts: 4
Groups: None

Hi,

I am currently migrating from P3 to P6.  In one of our reports - Variance Analyis in P3 filter I can define the filter the following:

if Actual dates Is WR DD-30D DD+0D

where Low Value = DD-30D

          High Value = DD+0D

In P6 the Actual dates is not there...  it was changed to something. I tried to use the Planned  Start or the Actual Start but the result was different than I expect. Can you help with this? Thanks.

 

Regards,

quartz

Rodel Marasigan
User offline. Last seen 3 hours 8 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Progress override means ignore the logic while Actual dates is not but using actual date when calculating forward pass and backward pass. Below is example of the difference.
Scheduling Options