Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline dates problems

5 replies [Last post]
Huzzle McNeive
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 8 Apr 2009
Posts: 6
Hi All!

I am having troubles with the dates on my new baseline. I have updated my current project and I wanted this as my new baseline. When I assign my current project as my new baseline, the dates on Baseline start and Baseline finish columns are different from the actuals. Please can anybody help me with this?

Replies

A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Huzzle / Paul,

Check the link below:

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=50178

Cheers,

Ravi
Rodel Marasigan
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Paul,
Thanks for the information and I always using that function but doesn’t solve the problem because it still follow the old logic from the baseline and will still show slippage. The only way is to change the planned date with current date and don’t run the schedule (F9). That will give exact replica of current schedule and save as a baseline. Meaning original duration will change and follow the current duration which will not the same if "Budgeted Value with current date" is used.
Paul Silver
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 30 Sep 2004
Posts: 16
Huzzle and Rodel,

There is a simpler way of overcoming this problem. In Admin Preferences under the Earned Value Tab, the Earned Value Calculation default is "Budgeted values with planned dates".

If you have the necessary authority, change this to the "Budgeted values with current dates" option. If you don’t have the authority you will need to discuss this with your system administrator. When you have made the change, copy your current project and assign it as a baseline and the dates will be aligned (as you would expect).

I hope this is of some assistance.

Regards
Paul Silver

Huzzle McNeive
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 8 Apr 2009
Posts: 6

Thanks a million Rodel
Rodel Marasigan
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699