Target Project Problem

3 replies [Last post]
James Braghini
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
Help!! When I create a traget project and do an update, the target bar is moving also. I have some project that does not do that and some that do. Is there something I need to uncheck or differently?

James B.

Replies

Pranab Kumar Deb
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello James,

One more mistake maybe that you assigned the Target correctly but while selecting the target bar from format>bar in bar description you selected the wrong start/finish . Format>bar ,You have to select target bar or make a new target Bar and assign - Target 1 Early start for start and Target 1 Early finish for finish


regards


deb
Raj Radhakrishnan
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 11 May 2004
Posts: 18
Groups: None
Hi James,

If you have already created a target and assigned the same, then the bars moving along with the current bars can be of 2 reasons.

1. you might have created the schedule target, but forgot to assign it as the primary basleine. in which case, the target bars you see at the bottom are just the current schedule bars showing up as target bars.

2. you might have forgotten to check cell to display the primary baseline bars. You can do that by clicking on the bar options, and check the box against the primary baseline to be displayed.

Hope this helps.

raj
Pranab Kumar Deb
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello James,

Unless you UPDATE TARGET , Tools>Project Uilities> Target and then update , selecting the required updates , it should not update the target and the taret bars should not move.
If you want you can send me the schedule to pranab.deb@akdn-pcm.org and i will check it for you.

regards
pranab