Lift erection schedule

1 reply [Last post]
Rohit K
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 2 May 2008
Posts: 73
dear all

can anyone of you provide me with an erection schedule for passenger lifts.

regards

rohit k

Replies

Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Rohit,

Please find below the sequence or erection of a Lift for since no one answered this question yet:

1. Site Survey of Lift Shaft
2. Installation of Rails
3. Installation of Door Frames
4. Installation of Outside Doors, Indicators and push buttons
5. Assembly of Cabin
6. Installation of Motor
7. Main Cable Installation, Connection to BMS if applicable.
8. Testing
9. Complete Installation of Interior Finishes
10. Balancing and Commissioning

These are the basic steps, other requirements will apply per specifications.

Good luck,

Samer