Piping Erection Rate

16 replies [Last post]
Mahmoud aly
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 18 Jun 2004
Posts: 4
Hi all;
Can any body tell me a reference to calculate the required manhour to erect piping spool per linear meter. Avtivities are:
-Erection,Tack
-Welded/Bolted
-Supported
-Inspection (RT,PT,---)
-Pressure Test
-Flushing
-Reinstatement

Thanks to all;

Replies

John Kuypers
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 21 Feb 2012
Posts: 3
Groups: None

Suggest you have a look at www.costeng.com. They have Estmating software that automatically accesses manhour data for all fabrication and or installation activities for pipework. 

Salim Mekki
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 10 Sep 2003
Posts: 55
The production rates depends on the type of material, thikness and pipe diameter. Better to distinguish between small and large bore, the rates are totaly differents. Use inch for estimating the progress of welding and tonnage for estimating the errection progress.

Hope that will help you.

Regards.
Philip Jonker
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Daya,

Thanks, but this is our daily bread so to speak, we get paid to think, and thinking is about asking questions about what you don’t know rather than what you know. To a lot of people thinking means dreaming about something nice.
Regards

Philip
Dayanidhi Dhandapany
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
you are great Philip, giving answers by questions
Philip Jonker
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Where is the guy working?
What is the specs?
What is the material?
What is the schedule of pipe?
Is heat treatment required?
Is HAZOPS a question?
What is the NDE requiorements?
Kow many Questions are there?
Think it through/
Dayanidhi Dhandapany
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Hello Sukumar,

I think you can refer Estimator’s Piping Man-hours manual by John S. Page that will cover those items in detail.

HTH

Daya
DATTATREYA PADHARTHI
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
I beg to differ on this issue.
Refinery/Petrochem Projects are demanding & much more complicated than building works.
Piping works are not so simple as Civil/Structural or building works.
Study & decipher Piping GAD’s & ISO’s, Piping materials are huge & diverse unlike Civil/structural materials.
Fabrication & erection have different rates,
Site fabrication, Shop fabrication, Pre-fabricated spools are have different welding rates which also depends on the Material of Construction (MOC) & ofcourse craftsmanship.
SAme is with Piping erection, since this involves work at site, its productivity is low compared to fabrication.
Factors affecting erection rate are MOC, Height of erection, Erection of Pipe Rack or around Equipments & others.
Piping work does not end here.
In fact, it will serve all if the various productivity rates are displayed (country-wise, job-wise etc), but will planners share such vital information?????


Sukumaran Subaram...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Jaco,

About the book. What is the name? Who is the author? Appreciate your info.

Regards.
Jaco Stadler
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
It is nice to so such an old Post came alive.

Well for me the easy method is to do an estimate.

Below Major Pointers for doing an estimate. (The Easy way is to take it from a book)

First we have a look at the Delivery. = HOW WILL THE PIPE GET THERE. Once we know this we can estimate an delivery estimate.

Then we have a look at Fitup = What type of pipe is it is. Is it Seamed / Seamless / Finwall / Thik Wall / Rolled / Spiral/ preped / macine prep. All This can effect the the time for the Fitup

Then we have a look at the Weld it self. I would suggest only work with Arc Time then Add Reel / Rod Changes / Setup etc. (The Reason with different method of Welding Example Stick / Mig etc) Will have differnet time Then you add Effeciency / Job Difuiculty Factors / QA / Material Type / etc.

Now you should have a good time for a weld.
Sukumaran Subaram...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
In piping fabrication the productivity rate is calculate based on dia inch ie. How many dia inch of weld per hour? Usually 22~25 dia inch.

Regards.
Ajay Sinha
User offline. Last seen 19 years 35 weeks ago. Offline
Joined: 26 Aug 2004
Posts: 3
What should be the measure of Piping Fabrication ? The concept of inch dia ignores the thickness. The concept of tonnage ignores the no. of joints.

In my opinion, the best (but cumbersome) is the volume of weld deposit that will give the most accurate information on the work content involved.

Any suggestions?
Zq qz
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Try also 3.752 Manhours per dia inch. this includes hanndling , fabrication, to final acceptance.
Dayanidhi Dhandapany
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
To calculate average number of welds by hour for pipe sizes over 30", you can use the following thumb rule:

N = 100/Pi*D,
where
D = Pipe Diameter,
Pi = 22/7 =3.14
D = 42 in your case
supplying all above info into the above thumb rule equation, you will get

N = 0.758 nos per hour, if it is 10hrs of working, 7.58 ~ 7 welds per day.

hopefully the above can help u to some extent.

Regards
Daya
Mahmoud aly
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 18 Jun 2004
Posts: 4
Can I know the production rate of 42" STD,CS Pipe (the work includes positioning,fitup,welding,supporting)?.
Thanks
Bernard Ertl
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Hi Mahmoud, welcome to the Planning Planet.

There are variables that will affect the estimates (metalurgy, diameter, thickness, #welds, etc.). We have a system that can assist you with preparing estimates, plans and schedules for piping erection, but it is not free (see link below).

Bernard Ertl