Al Turki Enterprises - Oman Planner

START Date: 
February, 2001
END Date: 
February, 2002
AL TURKI – OMAN - PETROLEUM DEVELOPMENT OMAN ENGG.SERVICE CONTRACT
REPORTING TO: Site Manager               
•     Database preparation and maintenance for job orders in Excel 2000
•     Daily meeting with works coordinator for Job Orders Exe.Plan with Plant Allocation
•     14 days / 90 days Rolling Plans in Microsoft Project 98(active job orders only) for New Flow lines Installation,HDPE Lining works, Wellheads preparation, Station jobs etc.
•     Weekly meeting with PDO Construction in charge along with site manager.
•     Invoicing documents tracking and monthly valuation report on money realized