Robertson Construction Group Civil Engineer
START Date:
January, 2002
END Date:
March, 2003 Robertson Group (Scotland),
Jan to March 2003, Site Agent.
£8 million Tesco Supermarket.
Supervised the laying of the internal drainage, ensuring its correct and timely completion prior to the ground floor slab pour on a challenging programme.
Following this I co-ordinated the installation of the electrical and mechanical services and plant. This included the design of service routes and the programming of deliveries and works.
March 2002 to Jan 2003, Site Agent.
£4.5 million ‘ring fenced’ Office Block Development at Dounreay.
I was involved before the start of works drafting significant parts of a rigorous Health and Safety Plan and the Quality Plan. Responsibilities included the management of all sub-contractors from groundworks through steel erection to finishing trades, maintaining a high standard of health and safety and quality. I was directly responsible for QA with weekly audits from a UKAEA representative.
Jan to March 2002, Site Agent.
£3.5 million Tesco Supermarket.
I safely managed the successful completion of a fast track build of a clad, steel framed structure. I co-ordinated the crainage for numerous lifts of plant and materials. Duties included setting out and all health and safety management.
Jan to March 2003, Site Agent.
£8 million Tesco Supermarket.
Supervised the laying of the internal drainage, ensuring its correct and timely completion prior to the ground floor slab pour on a challenging programme.
Following this I co-ordinated the installation of the electrical and mechanical services and plant. This included the design of service routes and the programming of deliveries and works.
March 2002 to Jan 2003, Site Agent.
£4.5 million ‘ring fenced’ Office Block Development at Dounreay.
I was involved before the start of works drafting significant parts of a rigorous Health and Safety Plan and the Quality Plan. Responsibilities included the management of all sub-contractors from groundworks through steel erection to finishing trades, maintaining a high standard of health and safety and quality. I was directly responsible for QA with weekly audits from a UKAEA representative.
Jan to March 2002, Site Agent.
£3.5 million Tesco Supermarket.
I safely managed the successful completion of a fast track build of a clad, steel framed structure. I co-ordinated the crainage for numerous lifts of plant and materials. Duties included setting out and all health and safety management.