Assistant / Planning Engineer, COWI, Railway Upgrading

START Date: 
February, 2002

Sr. Engineer - Railways, Alignment Design Engineer, Project Planning and Scheduling, Project management

Planning Engineer, MECC, A Subsidiary of Ali Alghanim & Sons, Installation of Flowlines

START Date: 
March, 2013

Planning Engineer working for Oil & Gas sector on Flow lines Project

Planning Engineer, MECC, A Subsidiary of Ali Alghanim & Sons, Installation of Flowlines

START Date: 
March, 2013

Planning Engineer working for Oil & Gas sector on Flow lines Project

Planning Engineer, MECC, A Subsidiary of Ali Alghanim & Sons, Installation of Flowlines

START Date: 
March, 2013

Planning Engineer working for Oil & Gas sector on Flow lines Project

EPC Senior Planner, Larsen & Toubro - ECC, Bangalore Metro Rail Project

START Date: 
January, 2009
END Date: 
August, 2010

1.      Overall responsibility of Planning – Viaduct in co-ordination with the Stations team

2.      Schedule preparation, monitoring progress and updating schedule (Initial schedule with MSP and subsequently working on P6 package).

3.      CPM Programme for Viaduct Project.

4.      Updating the Baseline Programme & Recovery Programmes.

Lead Project Planner EPCM, Fluor, New Synfuels Reactor Projects

START Date: 
January, 2009
END Date: 
July, 2010

Project Lead Planner responsible for developing, implimenting and maintaining project schedules and progress reporting and control systems.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Forensic Analysis): 
500

Senior planning engineer, M+W Group, Industrial

START Date: 
May, 2008
END Date: 
March, 2012

 

 

Ø  Site Start Up and Creation of Necessary Documents.

Ø  Making of L1, L2 and L3 Schedule.

Ø  Planning of the Project with respect to Mile stone and Priority

Ø  Derivation of Package wise Weightage and Progress Curve Projections

Ø  Coordination with Design Consultant, contractor and Client

Senior planning engineer, M+W Group, Industrial

START Date: 
May, 2008
END Date: 
March, 2012

 

 

Ø  Site Start Up and Creation of Necessary Documents.

Ø  Making of L1, L2 and L3 Schedule.

Ø  Planning of the Project with respect to Mile stone and Priority

Ø  Derivation of Package wise Weightage and Progress Curve Projections

Ø  Coordination with Design Consultant, contractor and Client

Construction management: , SOGEFINSA, Multi-use stadium in Granada, Spain. 22.524 spectators

START Date: 
September, 1993
END Date: 
June, 1995

Specialist Planner. Target plan and weekly control. Prefabricated Precast Concrete multi-use stadium.

Construction management: Project Planning, Bid Analysis, Scheduling, time-cost control and reporting. 

Project Director, IPECC Consultants, SHELL PAKISTAN LIMITED - Safety & Security Project at LOBP Keamari

START Date: 
April, 2011
END Date: 
September, 2011

 

SHELL PAKISTAN LIMITED - Safety & Security Project at LOBP Keamari

  • April 2011 to September 2011

Supply, Installation & Commissioning of Safety & Security Items at Main Gate of LOBP Keamari

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.