)Planning

Planning/Reporting Officer, Total E&P Nigeria, OML58-Upgrade Obagi

START Date: 
October, 2010
END Date: 
April, 2011

 

  • Monitoring of the Project schedule and reporting of any constraint or deviation to the overall Project Plan.
  • Collate daily man-hours for activities on a detailed basis and roll up to weekly summary report.
  • Follow up on Project quantities by checking, comparing & reporting actual quantities against planned quantities weekly.
  • Measurement and reporting of work progress on a weekly basis.
  • Verification of progress on activities submitted by EPC contractors.
  • Preparation of daily, weekly and monthly progress report.

Assistant Engineer - Planning & Project Control , Petronas Carigali Sdn Bhd, Sarawak

START Date: 
May, 2013
END Date: 
March, 2004

 Company: PETRONAS (MalaysiaOil Company as one of the most reputable international oil company)

         Position: Senior Project Control Engineer

             Year: 2013 -ongoing

 

           

 

Assistant Engineer - Planning & Project Control , Petronas Carigali Sdn Bhd, Sarawak

START Date: 
May, 2013
END Date: 
March, 2004

 Company: PETRONAS (MalaysiaOil Company as one of the most reputable international oil company)

         Position: Senior Project Control Engineer

             Year: 2013 -ongoing

 

           

 

Director, Ten Six Consulting, Multiple

START Date: 
January, 2011

Ten Six Consulting specializes in implementing Enterprise Project Management (EPM), Project Portfolio Management (PPM) and Earned Value Management (EVM) solutions. Our consultants have successfully implemented these solutions in many industries, including Aerospace and Defense, IT, Media, Energy, Telecom, Public Sector and Finance.

Planning Engineer, Anwar Ali & Associates, Parliament Lodges Extension Project

START Date: 
November, 2012
  • Planning & Scehduling, Progress Reports, Progress Monitoring, Progress Updates
  • Progress Reports, Presentations
  • Corrspondance with contractor, client

Cost Engineer/Assistant Planning Engineer, Carillion Plc - Transport - London Projects, Railway Infrastructur

START Date: 
March, 1998
Cost Engineer/Surveyor Involved in highways and rail schemes Estimating Project Controls Claims Commercial support Change Management

Cost Engineer/Assistant Planning Engineer, Carillion Plc - Transport - London Projects, Railway Infrastructur

START Date: 
March, 1998
Cost Engineer/Surveyor Involved in highways and rail schemes Estimating Project Controls Claims Commercial support Change Management

Cost Engineer/Assistant Planning Engineer, Carillion Plc - Transport - London Projects, Railway Infrastructur

START Date: 
March, 1998
Cost Engineer/Surveyor Involved in highways and rail schemes Estimating Project Controls Claims Commercial support Change Management

Cost Engineer/Assistant Planning Engineer, Carillion Plc - Transport - London Projects, Railway Infrastructur

START Date: 
March, 1998
Cost Engineer/Surveyor Involved in highways and rail schemes Estimating Project Controls Claims Commercial support Change Management

Planner Engineer, CCE - Contracting & Construction Enterprise Ltd., SADARA Poly Ethylene

START Date: 
December, 2012

RESPONSIBILITIES
● Prepare and update project schedule based on the contract. 
● Set work program and target milestones for each phase based on the project plan.<

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content