%100- Project Planning; Progress Reporting; Primavera P6; Master Schedule

ANALYST / PLANNING ENGINEER, DF Energy, Central Vuelta de Obligado

START Date: 
October, 2012
END Date: 
August, 2014

Project Controls & Site Planning Engineer in a 810MW Power Plant in Argentina.

Project: CCGT 810 MW - GE STAG 209FA Multi-Shaft. Central Termoeléctrica Vuelta de Obligado.

Location: Timbúes (Argentina)

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Forensic Analysis): 
150

PROJECT PLANNER, EXPERIS MAN POWER / PACIFIC E&P, project Planner at Pacific E&P - oil & gas

START Date: 
May, 2015
END Date: 
May, 2016

Duties:

Projects control and planning

·         Structuring portfolio, programs and projects BLOCK Z1 "OFFSHORE"

·         Support project portfolio budget estimate.

·         Support project team in analyzing scope of work, definition of WBS, implementation, execution plan optimization and risk management.

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
1350
Experience Hours (Forensic Analysis): 
250

Field Scheduler, SIEMENS AKTIENGESELLSCHAFT, EGAT / CHANA / CCPP1

START Date: 
April, 2007
END Date: 
February, 2008

Responsibilities Prepare logical network of activities and ultimately a critical path schedule. Conduct weekly meeting with all Engineers to discuss schedule progress and forecasting plan. Field visit to visualize progress and ensure high accuracy data provided. Add resource allocation, as needed. Produce graphical charts & reports to be reported weekly to manager

Experience Hours (Planning & Scheduling): 
950

Planner, WORLEYPARSONS (Thailand) Limited , Pluto LNG Project

START Date: 
March, 2008
END Date: 
August, 2009

Responsibilities Develop level 4 schedule with monitoring and controlling project master schedule. Weekly progress report preparation reported to Construction Manager

Experience Hours (Planning & Scheduling): 
1500

Senior Turnaround Planner, Exxon Mobil (Thailand), Exxonmobil - IE11

START Date: 
February, 2011
END Date: 
July, 2011

Responsibilities to incorporate with multiple departments detailed schedule and work plans and perform inclusive schedule analysis, Report T/A Manager on progress monitoring in relation to detailed schedule and work plans with an executive summary report. Support the measurement and improvement of KPI targets (Time and Cost compliance to schedule)

Experience Hours (Planning & Scheduling): 
1000

Planner, Marubeni Corporation, EGAT / Wangnoi / CCPP4

START Date: 
July, 2011
END Date: 
March, 2013

Responsibilities to review and prepare EPC contract of power plant master schedule, progress measurement and progress report to management including contractor level-4 schedule integration, to review and advise action required for recovery schedule to contractors

Experience Hours (Planning & Scheduling): 
4000

Senior Planner / Scheduler, CUEL Limited, Ichthys LNG Project

START Date: 
April, 2013
END Date: 
January, 2016

Develop project master plan with contractors and implementing  project master schedule updating. Weekly / Monthly progress report preparation reported to Project Control Manager 

 lead the project planning on a large project, train planning personnel within the project and develop medhodology and procedure tailored to clients special requirement including to work closely with claim team for schedule impact analysis with forensic schedule intensive skill.

Experience Hours (Planning & Scheduling): 
4200
Experience Hours (Forensic Analysis): 
1600

Head of Scheduling, Babcock, Aircraft carrier

START Date: 
June, 2007

Head of scheduling, leading a team of more than 12 schedulers working in P6 on fully resource loaded schedules worth approx £1bn

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Site Scheduler, BP, Sullom Voe Oil Terminal ( Onshore Oil Terminal)

START Date: 
September, 2014
END Date: 
June, 2015

(Rotational Working 2 Weeks on 3 Weeks Off)

Site Scheduler

Responsible for delivering a 2 Week agreed resource balanced Site Execution Schedule for the whole of Sullom Voe Oil and Gas Terminal in the Shetland Islands. 

Experience Hours (Planning & Scheduling): 
1600

Commissioning Planner, BAE SYSTEMS (Naval Ships), Aircraft Alliance for new Queen Elisabeth Class.

START Date: 
July, 2015
END Date: 
January, 2016

(Contractor)

Commissioning Planner on 1st of Class QNLZ Royal Navy Air Craft Carrier.

Working with the Lead Commissioning Planner to deliver a very complex schedule.

Introduced Structured Weekly Progress Collation and Reporting and Assisted with Management Reporting.

Experience Hours (Planning & Scheduling): 
1000