Schedule Control Manager, ILF Consulting Engineers, Kazakhstan China Gas Pipeline

START Date: 
July, 2013

Schedule Control Manager

1.Developed project dash board, delay analysis, assisting the AGP (Client) and their EPCC contractors in developing their recovery plan, provide recommendation to the Client with regards to the delays and forecasting the remaining works to meet the contractual milestone date.

2. Preparing a weekly and monthly report to the client, update the overall progress s-curves, reviewing the progress measurement system from the EPCC contractors, submitting an analysis of the project twice a month.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
21500

Schedule Control Manager, ILF Consulting Engineers, Kazakhstan China Gas Pipeline

START Date: 
July, 2013

Schedule Control Manager

1.Developed project dash board, delay analysis, assisting the AGP (Client) and their EPCC contractors in developing their recovery plan, provide recommendation to the Client with regards to the delays and forecasting the remaining works to meet the contractual milestone date.

2. Preparing a weekly and monthly report to the client, update the overall progress s-curves, reviewing the progress measurement system from the EPCC contractors, submitting an analysis of the project twice a month.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
21500

Schedule Control Manager, ILF Consulting Engineers, Kazakhstan China Gas Pipeline

START Date: 
July, 2013

Schedule Control Manager

1.Developed project dash board, delay analysis, assisting the AGP (Client) and their EPCC contractors in developing their recovery plan, provide recommendation to the Client with regards to the delays and forecasting the remaining works to meet the contractual milestone date.

2. Preparing a weekly and monthly report to the client, update the overall progress s-curves, reviewing the progress measurement system from the EPCC contractors, submitting an analysis of the project twice a month.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
21500

Ionut Marinescu

First Name: 
Ionut
Last Name: 
Marinescu

Current position: Offshore Senior planning, reporting & risk engineer  

Professional Since: 
Oct-1990 (33.6 yrs experience)
Oldest experience: 
Jul 1993 (30.8 yrs experience, WARNING: 2.7 years variance with Professional Since)
Years Experience: 
20

Bid Engineer / Workforce planner, CHEMIMONTAZH LTD, Maintenance work at KTL 1 & KTL 2

START Date: 
October, 2013
During my work I responsible for mainly, but not limited to, the following tasks: Workforce Planning;Bid preparation;Document preparation;Drawing preparation;Calculations;Equipent productivity calculations;Progress reporting; Conctracts preparation;

Bid Engineer / Workforce planner, CHEMIMONTAZH LTD, Maintenance work at KTL 1 & KTL 2

START Date: 
October, 2013
During my work I responsible for mainly, but not limited to, the following tasks: Workforce Planning; Bid preparation; Document preparation; Drawing preparation; Calculations; Equipent productivity calculations; Progress reporting; Conctracts preparation;

Bid Engineer / Workforce planner, CHEMIMONTAZH LTD, Maintenance work at KTL 1 & KTL 2

START Date: 
October, 2013
  • During my work I responsible for mainly, but not limited to, the following tasks:
  • Workforce Planning;
  • Bid preparation;
  • Document preparation;
  • Drawing preparation;
  • Calculations;
  • Equipent productivity calculations;
  • Progress reporting;
  • Conctracts preparation;

Szűcs Zsolt

First Name: 
Szűcs
Last Name: 
Zsolt
Oldest experience: 
Apr 2010 (14.1 yrs experience, WARNING: 40.2 years variance with Professional Since)
Years Experience: 
3

Bid Engineer / Workforce planner, CHEMIMONTAZH LTD, Maintenance work at KTL 1 & KTL 2

START Date: 
October, 2013

My responsibilities are:

Bid preparation, workforce planning, preparation of the document related to the bids.

Bid Engineer / Workforce planner, CHEMIMONTAZH LTD, Maintenance work at KTL 1 & KTL 2

START Date: 
April, 2010

My responsibilities are:

  • Calculations;
  • Workforce Planning;
  • Progress Reporting;
  • Preparation of documents related to the maintenance works;