Project Planning Co-ordinator, Scottish Water, (various projects)

START Date: 
March, 2013

Responsible for the monitoring and updating of a broad portfolio of water/waste water projects througout the country.

Project Manager, Network Rail, (various projects)

START Date: 
October, 2011

5 years Network Rail

Msc Programme and Project Management - Warwick University

APMP

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
150

Project Manager, Network Rail, (various projects)

START Date: 
October, 2011

5 years Network Rail

Msc Programme and Project Management - Warwick University

APMP

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
150

Junior Engineer, Fathy Abd Rabu Construction Berau, (various projects)

START Date: 
November, 2002
END Date: 
February, 2005

I have worked on multiple building construction projects in Egypt as a junior engineer. I participated in three medium sized projects all in Alexandria

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
1500

Construction Planner, Group Five Coastal, (various projects)

START Date: 
December, 2014
END Date: 
January, 2016

· Recently started with Autodesk software & Linking the CCS programme to a 3D Revit Model         

Studying tender document (Contract, drawings, specifications, reports etc)

·         Extracting information which might be risk to our business unit, identifying opportunities and defining whether or not the timeframe given is achievable

Senior Planning Consultant, Sporle Consultancy Services (SCS), (various projects)

START Date: 
December, 2009
  • Windows Analysis - Extracting, analysing and comparing critical paths of contemporaneous schedules.
  • Review contract documents and identify requirements regarding project controls and Entitlement to EOT and associated costs.
  • Carrying out appropriate analytical techniques to demonstrate Contractor’s Entitlement to EOT and associated costs.
  • Prepare Statement of Claims (detailed reports and analyses).
  • Provided assistance to the appointed Expert in relation to delay assessment on a Contractor’s Claim.
  • Perform delay a
Experience Hours (Forensic Analysis): 
13250

Planning Consultant, First Line Consultancy, (various projects)

START Date: 
April, 2008
END Date: 
November, 2009
  • Prepare Preliminary Project Construction Programme & Method Statement for Tender submissions.
  • Prepare detailed programme & Method Statement for Construction.
  • Conduct Meeting with site engineer’s for reviewing progress.
  • Update the Construction Schedules.
  • Prepare delay-notices to Engineer in regards to Employer’s delay events.
  • Conduct delay analysis and prepare Detailed Particulars (Contractor’s claims) for Extension of Time using recognised construction industry methods applicable to the contract conditions.
  • Review and provide resp
Experience Hours (Planning & Scheduling): 
1250
Experience Hours (Forensic Analysis): 
2000

Planning Engineer, Ahmadiah Contracting & Trading Co. KCSC, (various projects)

START Date: 
May, 2005
END Date: 
March, 2008
  • Prepare Schedule for Design Development & Construction Documentation.
  • Prepare preliminary construction strategy.
  • Prepared and Monitor Design Development & Construction Documentation schedule.
  • Prepare and Monitor Contractor Baseline Programmes including Resources and Cost.
  • Attend Progress meetings with Project Manager/Consultants.
  • Conduct Sub-contractors Progress & Coordination meetings.
  • Identifying the critical activities that must be performed to produce the various project deliverables.
  • Preparing performance measurem
Experience Hours (Planning & Scheduling): 
5750

Planning Engineer, Construction, (various projects)

START Date: 
August, 1997
END Date: 
April, 2005
  • Prepare Comprehensive Monthly Project Progress Reports for the Project Stakeholders
  • Prepare Contractors Construction Schedule (using CPM & PERT)
  • Prepare Schedule of Values / Cost Loading, Resource analysis and Cash Flow Projections.
  • Prepare weekly and monthly “Look Ahead Programs” for site-engineers, Update the project schedules.
  • Material selection, Submittal, Ordering & Procurement
  • Prepare Report for the Management and Clients
  • Monitoring of Sites Activities to ensure align
Experience Hours (Planning & Scheduling): 
15400

Engineer / Project Engineer, DC Associates, (various projects)

START Date: 
November, 2002
END Date: 
September, 2003

Fire alarm programming, scheduling, RFIs, Submittal management, wharehouse management, device and material takeoffs for field orders. 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content