Setting up of detailed baseline program with Primavera P6; prepared BoQ cost breakdown activity wise and loading baseline program activities with cost, quantity and manpower resources; issued start-up programmes to project team; Preparation of engineering (shop drawing, material and method statement) schedules and long lead procurement schedules in line with baseline programme; Setting up of progress measurement system including kpi’s and dashboard; Preparation of S-curves for cash flow; Updating baseline programme and reviewing it with project team; Prepared client progress reports and pre