Project Scheduler

Project Scheduler, Trojan Holding, Abu dhabi marina bloom development

START Date: 
September, 2014

*Monitoring and Controlling the master baseline schedule in P6

*Performing weekly updates on the baseline

*Generating weekly S-Curve to present in the weekly progress meetings to the client

*Assisting the project manager to calculate the required manpower for the coming month in conjunction with the planned manpower as per the master baseline

*Variance analysis to show any delay from other parties

*Generating planned vs actual values to the higher management to measure the performance of the project

Experience Hours (Planning & Scheduling): 
450

Project Scheduler, The Agile Group, LLC, Afghanistan National Security Facilities

START Date: 
September, 2011
END Date: 
May, 2012

Provided scheduling support for the Transatlantic Division, U.S. Army Corps of Engineers, in scheduling civil construction projects for the Afghanistan National Army and Police forces.

Experience Hours (Planning & Scheduling): 
700

Project Scheduler, The Agile Group, LLC, Afghanistan National Security Facilities

START Date: 
September, 2011
END Date: 
May, 2012

Provided scheduling support for the Transatlantic Division, U.S. Army Corps of Engineers, in scheduling civil construction projects for the Afghanistan National Army and Police forces.

Experience Hours (Planning & Scheduling): 
700

Project Scheduler, APA-Group, Gas Infrastructure

START Date: 
March, 2013

Preparing schedules for new projects, assisting with contractor scrutiny during tender submissions, reviewing schedules for extension of time claims, providing support to PM's on scheduling matters.

Preparing monthly reports for Steering committee.

Being everyone's Bitch - I also help out with construction management and supervision.

Trying to convince people to use a decent scheduling tool like Asta or TILOS, some still think the world is flat!

Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Forensic Analysis): 
4000

Project Scheduler, Worley Parsons, BHPBIO Hunt Piont Tug Harbour Project

START Date: 
January, 2012
END Date: 
July, 2012

 

Worley Parsons - BHP Hunt Point Tug harbour Project 

  • Working with a senior planner develop a fully resources execution schedule to BHPBIO requirement for the $700 million 24 berth Tug Harbour in Port Hedland with supporting land facilities.
  • „  Integration of scope changes and What-If Scenarios to identify potential savings and or recovery to schedule durations and costs. 

Project Scheduler, PT. Vale Indonesia Tbk, Various capital projects

START Date: 
June, 2013

I'm as Projert Scheduler of PT. Vale Indonesia Tbk since Jun 2013. PT Vale Indonesia Tbk is an Indonesian mining nickel company based on Sorowako, South Sulawesi.

Project Scheduler, James G. Davis Construction Corp, (various projects)

START Date: 
November, 2013
END Date: 
October, 2015

Project Scheduler.  Responsible for providing technical support and education to the operations staff in CPM scheduling at the project level. Reviewed schedules with project teams to ensure schedules were being developed properly. Also assisted the Director of Scheduling with developing schedules for presentations and proposals.

Project Scheduler, Tenix Pty Ltd, ANZAC Ship Project

START Date: 
November, 1990
END Date: 
August, 2002

Project Scheduler 

September 1993 – August 2002

  • Project Control:
  • Schedule Development and Maintenance:
  • Budget Allocation:
  • Resource Utilisation:
  • Facility Availability:
  • Time Management:
  • Training:

Planner (Work Prep) 

April 1992 –September 1993

  • Work Order Preparation
  • Minor Schedule Development
  • Material Takeoffs

Planner (Work Centre)

November 1990 – April 1992

  • Work Allocation

Project Scheduler, Babcock, (Radwaste & Decommissioning Project)

START Date: 
May, 2013

An integral part of a planning/scheduling team, responsible for scheduling functions associated with fabrication, construction, engineering and installation associated with the decomissioning on the Sellafield project. Reporting directly to the planning team lead and functionally to the associated project manager.

Project Scheduler, Swift, TGPE Project

START Date: 
January, 2011

Project Scheduler for gas plant expansion in Tioga, North Dakota.